adding sub tasks in Outlook


Just trying out Todoist for the first time.

I can add sub tasks within the android app. Is there a way to do this in outlook

Thanks Jon

All responses

David Trey  staff
Replied on Jan 10, 2014 - 13:01 UTC

Hello Jon,

Yes, you can add sub-tasks on any platform. They can only be added while you're within a project, though.

To add a sub-task:
- Enter a project
- Click on "Add task" at the bottom
- Use the arrow icons on the right or Ctrl+RightArrow and Ctrl+LeftArrow to indent/unindent a task.

You can also indent any existing task after clicking on it to open the edit field or, if you want to add the sub-task under a specific existing task, right-click on the task and choose "Add task below".

Best regards,