+ Add Question

Implementation of MYN


is there a way to implement the MYN principles in Todoist? There is one thing that i'm not able to do: setting a start date of a task and don't display it as long as it is not started. Is it possible to do this? And if so: how?



All responses

David Trey  staff
Replied on Oct 09, 2013 - 11:41 UTC

Hello Ben,

This is possible if you set a task to a date such as "every day starting 20 Nov". You will see such task only within its project, but it won't show up on any date-based view until its first recurrence.

Best regards,

Benjamin Bachmann
Replied on Oct 09, 2013 - 15:43 UTC

Hi David,

thanks - gonna give this a try. I'll have to look deeper into Todoist. Seems to be quite nice, but I'll need my own customized view. But thank god weekend is soon...