I want to use after... but only on the next sunday...

Eg: I want the task to be repeated every sunday, but only after I completed the task

All responses

David Trey staff
Replied on Jan 27, 2013 - 08:51

Hello Castor,

Please use the following due date: "every Sunday" (or "ev Sun"). Each time you complete it, it will be scheduled for the next Sunday.


Best regards,
David

C
Castor
Replied on Jan 27, 2013 - 08:53

If i miss updating the task for 3 weeks, when I complete the task, are three more tasks created, or only one?

David Trey staff
Replied on Jan 27, 2013 - 08:56

Castor,

Every recurring tasks is only added as one single task scheduled for a certain due date, but unlike a non-recurring tasks, when you complete it, instead of disappearing, it's being rescheduled to the next event according to its recurrence formula.

For example - you add a task due "every Sunday", you complete it and in this moment, the same task becomes due next Sunday. If you miss it and it becomes overdue, once you check it off, it will be due next Sunday and it will recur forever until you right-click on it and choose "Move to history" or hold the SHIFT key while checking it off.