Problem with recurring dates.

Hi!

How can I start new task which due date is each 90 days but first time it's at 31 August. I've tried typing "every 90 days since 31 August" and like but then always first due date is set as "today".
Any ideas?

Adrian

Asked by on Aug 26, 2011 - 03:48

on Aug 26, 2011 - 04:07

Hi Adrian,

try this:

every 90 days starting aug 31


Raimi

on Aug 26, 2011 - 04:12

Thank you very much, it worked. Odd, that I didn't try.