Outlook tasks have wrong times
WHen I create a task in Todoist, it appears in my Outlook calendar 8 hours later than the time I entered in Todoist
Asked by Michael Vachon on Oct 06, 2012 - 09:07
David Trey
on Oct 06, 2012 - 10:12
Hello Michael,
thank you very much for your report, I have passed it to the developers and we'll try to fix this issue as soon as we can. Sorry for the inconvenience.
Best regards,
David
David Trey
on Nov 13, 2012 - 12:37
Hello,
This issue should now be fixed. Please try to re-add your calendar feed to your calendar software and let us know if you continue to experience this issue.
Best regards,
David