Is there a way to setup projects/or task to be weekday or weekend only so the late counter excludes days not in this range. Ex. You make a task late after 4 days but you are not working Saturday and Sunday but have these days counted against you. If not you should add this feature.

All responses

David Trey staff
Replied on Aug 18, 2014 - 13:20

Hello Wyatt,

That's not possible right now, at least not directly. You can't have a task due "every day", for example, postpone it on Friday and have it move to Monday, skipping the weekend, but you can use due dates such as "every weekday" or "every mon, tue, wed, thu, fri" or "every sat, sun" and if you postpone or complete them on the last day, they will jump to the next day according to their recurrence pattern.