BUG when editing parent task

T

Steps to reproduce the issue.
Add a task with subtasks.
View this task in time-based view or search-based view.
Edit this task.
The arrow on the left, allowing to expand the task has disappeared.

Please fix this issue.

Best Regards,

Thomas

All responses

David Trey staff
Replied on May 12, 2014 - 16:34

Hello Thomas,

I can only partially reproduce this issue - right after editing the arrow disappears, but moments after that, as the data syncs, it reappears again.

Please confirm if that's also what you're referring to or does it permanently disappear for you? If so - what exactly are you searching for and what browser are you using?


Best regards,
David

T
Thomas premium
Replied on May 12, 2014 - 16:47

Hi,

Yes, it does appear to be solved after about 3 or 4 seconds. Another issue: the tasks become collapsed after syncing.

David Trey staff
Replied on May 12, 2014 - 16:50

Thomas,

I'll pass it to the developers and we'll look into this.


Best regards,
David

T
Thomas premium
Replied on May 13, 2014 - 19:13

Hi David,

Any movement on this issue? it makes it very difficult to work with task hierarchies in the 7 days view.

David Trey staff
Replied on May 13, 2014 - 19:24

Thomas,

This issue has not been fixed yet. Please note that editing task hierarchies is best done in a project where you can also freely create sub-tasks, move them around etc.


Best regards,
David