Tasks are missing in "Next 7 days view"

S

Dear Sir/madam,
i have updated 8 task
1 task date = 23-Jan14
7 Task date = 24- Jan-14

when i view the list under " project " it showing all 8 task

but when i use " Next 7 Day " i can only see 5 Task ( 2 are missing )

All responses

David Trey staff
Replied on Jan 23, 2014 - 10:56

Hello Shobin,

Please tell me - is there anything different about these 2 tasks that are missing from the "Next 7 days" view? Do they have the exact correct date for the same day, month and year? If you notice anything that makes them different from the rest, please let us know, it would greatly help us identify the issue.


Best regards,
David