Hey,

I'd like to have a recurring task every 2nd Monday, starting with Feb 3rd

I tried "ev 2nd mon starting 3.2." and "ev 2nd mon starting +13" and even "ev 2nd mon after 2.2.", to no avail. Help?

Thx,
peter.


All responses

Brendon Wadey staff
Replied on Jan 21, 2014 - 21:52 UTC

Hi Peter,

The correct syntax would be "every second monday starting 3 feb". We do not currently support dates as you provided.

Thanks,
Brendon.

PS
Peter Sabaini premium
Replied on Jan 21, 2014 - 22:04 UTC

Unfortunately, that doesn't work either. C/P the above string still results in start date of Feb 10th.

Brendon Wadey staff
Replied on Jan 21, 2014 - 22:06 UTC

Peter,

Which is correct. As February 3 is not the second Monday, the 10th is.

Regards,
Brendon.

PS
Peter Sabaini premium
Replied on Jan 21, 2014 - 22:14 UTC

Oh, I see -- I guess I really wanted "every 14 days starting 3.2."

Thanks for the help

Brendon Wadey staff
Replied on Jan 21, 2014 - 22:27 UTC

Peter,

That is also possible, but I was thinking you wanted it the other way.
Your option would be "ev 14 days starting feb 3".

Thanks,
Brendon.

PS
Peter Sabaini premium
Replied on Jan 21, 2014 - 22:34 UTC

On my screen 3.2. works out to Feb 3rd, probably because of my date format settings? Anyway, it looks good now. Thanks again.