+ Add Question

setting up a template

CV

when I create a template can i assign the "due dates" out as days rather than specific dates. For instance I want to have a the 2nd task due 3 days after the 1st task is due - i have a total of 16 taks for the project. Currently I only see specific days and while that is great for the first time It do this ... it does not help on future projects.

thanks!

All responses

David Trey staff
Replied on Dec 27, 2013 - 12:56 UTC

Hello Chris,

Although you can't set a date to be "x days after the due date of another task", you can use +x to set it to a number of days "from now".

So, for example, one task can have a due date +2 and another +4 which will set the first to 2 days from now (the moment you upload the template) and the second to 4 days from now.


Best regards,
David