I experienced a bug with tasks that include subtasks.

1) I oftentimes click a task as complete in error. This is natural, because the checkbox looks like a selection box. If I click on the task header it marks all subtasks as complete. Is thewre any plan to address this?

2) BUG found - I checked a task in error (see above) and all the sub-tasks get checked automatically as completed (annoying). I tried to reverse the "complete status" and was not able to do so with the sub tasks. I lost them.

All responses

David Trey staff
Replied on Nov 25, 2013 - 12:58 UTC

Hello Greg,

If you un-complete the parent task from the "completed task" section in the bottom-right corner of the project in which the tasks have been completed, all sub-tasks should be restored along with the parent task.

If that wasn't the case, please tell me:
- From where exactly did you un-complete the parent task?
- Can you reproduce this issue with a test task and sub-task?
- What browser are you using?


Best regards,
David

Tom Brown premium
Replied on Oct 06, 2014 - 23:51 UTC

I've seen some similar cases today. I'll try to reproduce. More if I get anything clean.

AA
Alexandre Aleixo premium
Replied on Oct 07, 2014 - 00:44 UTC

Also have the same problem sometimes...

Eugenie Rivers premium
Replied on Nov 12, 2014 - 04:31 UTC

There is no "completed task" section in the bottom-right corner of the projects. There was one previously and it now is gone. Help!

Eugenie D. Rivers

Clyde Romo staff
Replied on Nov 12, 2014 - 05:05 UTC

Hi Eugene,

It should still be in the lower right corner of the screen. (See attachment)