+ Add Question

[Bug] Date parser doesn't recognise "8th Jan" when used with the "every" prefix

EM

STR:
1) Create a new task with name 'foo' and due date 'every 8th jan'
2) Click add task

Expected:
New task added that is set to reoccur once a year on 8th Jan.

Actual:
* "Invalid date" error shown.
* You have to instead use "every 8 jan" (ie without the "th")
* However using "8th jan" on its own (not reoccurring) works - guessing the regexp for the "every" prefix is just not handling the "th" case.

All responses

David Trey staff
Replied on Nov 24, 2013 - 22:57 UTC

Hello Ed,

Thank you for your report, I've passed it to the developers and we'll look into it.


Best regards,
David

EM
Ed Morley premium
Replied on Nov 25, 2013 - 09:04 UTC

Thank you :-)