is it somehow possible to link todos/tasks for example
"done date of task 2 = done date of task 1 + 2 days" or
"task 1 needs to be done before task 2"?

Thanks
Martin

All responses

Brendon Wadey staff
Replied on Oct 18, 2013 - 14:34 UTC

Hi Martin,

Unfortunately this isn't possible at this time. We will consider adding this ability in future updates. Feel free to add this to our Votebox: http://todoist.com/Vote/

Thanks,
Brendon.