+ Add Question

Is it possible to check a task as complete, but it will remain visible in the project list (not at bottom and greyed out with line through)

C

All responses

David Trey staff
Replied on Sep 30, 2013 - 20:04

Hello Cheryl,

This is only possible if it's a sub-task in which case it will stay on the list until you complete its parent task. All other task will move to the history which you can access through the icon in the bottom-right corner in the project.


Best regards,
David