+ Add Question

Can New Tasks Appear at Top of Project Task List?

BN

Is it possible to have newly added tasks appear at the top of a project task list?

Thanks,
Brian Norman

All responses

Brendon Wadey staff
Replied on May 06, 2013 - 13:21

Hi Brian,

At the moment, unfortunately, it's not possible to add every new task at the top by default, but you can right-click on the task that's currently at the top and choose "Add task above".

You can also quickly sort all your tasks by date or priority, and we recommend using due dates or priorities to be able to easily see the most important tasks at the top of the list.

Thanks,
Brendon.

BN
Brian Norman premium
Replied on May 06, 2013 - 14:27

That helps. Thanks, Brendon.