Hiberarchy level for reminder

PG

hi,

i have found some issue as below,

if one item with indent 3 in its project, then setting one target date.

Till the target date, the item will show as top indent inside the due date. But, for its chide(indent 4) still show his original indent. Not 4 - (3 -1) as indent 2.

some kinds of lost Parent Child Relationships changed to grandfather ...

All responses

David Trey staff
Replied on Dec 18, 2012 - 06:56

Hello Peter,

Could you please send a screenshot showing this issue to david@doist.io ?

Also, please note that if you're viewing tasks by date, all tasks that are due for this date will be shown without their indent levels unless they are parent tasks in which case they will have an arrow next to them allowing you to see their children for reference.