Bug: incorrectly checked off nested task

MM

Hi :)
Recently I've noticed "disappearing" tasks. There is some problem with checking off previously nested tasks.

Please repeat this scenario:
1. create new project "test"
2. create task "a" (keyboard: a, a, enter)
3. create subtask "aa" for task "a" (ctrl+right arrow, aa, enter)
4. create subtask "ab" for task "a" (ab, enter)
5. create subtask "ac" for task "a" (ac, enter)
Now [ESC] and click "ac" task. On keyboard press ctrl + left arrow to move it to root level (because I don't want it to be nested anymore). Enter to confirm.
Now using mouse check off task "a". Task "ac" is checked off with the rest of the tasks (even though it is not longer nested within task "a").

Sorry for lengthy description :).
Hope you'll be able to repeat it this way.

All responses

David Trey staff
Replied on Jul 30, 2012 - 03:18

Hello Michał,

I've been able to reproduce this issue and have passed it to the developers.

Thank you very much for reporting it and sorry for any inconvenience it might have caused you.


Best regards,
David

David Trey staff
Replied on Aug 01, 2012 - 00:41

Hello Michał,

this issue has been fixed, un-indented tasks will no longer remember their former indent level and be bound to their former parent task.


Best regards,
David

MM
Michał Małowski
Replied on Aug 01, 2012 - 21:18

Hi David.
Thanks a lot guys. I wasn't even expecting it to be fixed that fast :)

Regards,
Mike