how to show incomplete tasks only ?

MY

When I finish a task, I click the check-box to mark it complete. So, usually I want to show not completed task only, include task w/ due date and w/o due date. More importantly, I want to maintain the project hierarchy, so option such as "od" does not work for me. I could archive the finished task, but that moves it away from the project hierarchy. Similar like "overall", can we have a queue of "overall - incomplete" ?

All responses

David Trey staff
Replied on Feb 07, 2012 - 05:22 UTC

Hello Michael,

every non-project view shows just the incomplete tasks and within any project view, you can only see completed tasks if they're sub-tasks.

If you don't want sub-tasks to stay within the project view, please hold the SHIFT key while checking them off so they will be directly moved to the completed tasks list.

Unfortunately, there's no other way to view only unfinished tasks within a project view and keep finished sub-tasks within the task list, but thank you for your feedback, we appreciate it and may consider adding such option in future development.

You're welcome to add a request to our Votebox:
http://todoist.com/Vote/


Best regards,
David