+ Add Question

Repeating task every other week

JN

I am trying to set up a repeating task that happens every other Thursday at 5:30PM

I ma having a hard time coming up with the correct way to set this up

All responses

David Trey staff
Replied on Aug 31, 2011 - 03:36

Hello Joe,

please use the following formula:

every 14 days starting 1. Sep 2011

or replace the starting date with any other date you wish the task to begin at.


Best regards,
David

H
Hana
Replied on Sep 07, 2011 - 07:07

I have tried this solution also with no success. I'm a new user, is this a Premium only function?

David Trey staff
Replied on Sep 07, 2011 - 07:45

Hello Hana,

there has been a temporary issue with due dates containing "starting", but it has been fixed now.

Please try to use the above formula again and let me know if you still experience any issues.

Sorry for the inconvenience.


Best regards,
David

H
Hana
Replied on Sep 07, 2011 - 08:05

It works:-) I had to close out and reopen my session first, but now I'm all set - thank you David!